Atrisco Heritage High School 118th St. Road Improvements

Project Scope

Adding a curb and extending the trail along 118th St. in front of Atrisco Heritage High School.

Funding: The funding for this project is from the state.

General Project Information

Status | Completed
Project Engineer | Vincent Bartholdi
Project Manager | Don Mitchell
Construction | December 2018
Contractor | Albuquerque Asphalt
Construction Cost | $81,413.94
Construction Notice to Proceed | December 5, 2018
Project % Completed | 100%

Project Contact Information

Project Manager | Don Mitchell
Office Phone | (505) 848-1576
Cell Phone | (505) 301-6928