Alameda Boulevard Medians Landscape Renovation Phase II

Project Scope

Traffic Control Plan, (permitted through NMDOT). Removal, site preparation and grading of existing landscape. Excavate, verify and connect to existing lateral irrigation pipes. Install weed barrier fabric and landscape aggregate. Plant: (12ea.Desert Willow), (18 ea. Mountain Mahogany), (16 ea. Oriental fountain Grass), (16 ea. Dwarf Fountain Grass), (20 ea. Red Flowering Yucca), (16 ea. Twisted Leaf Yucca). 

General Project Information

Section | Parks & Recreation
Project Manager | Dennis Duran
Project Settlement Date | 8/5/15
Start Date | 8/17/15
Completion Date | 9/10/15

Deliverables Due | 9/30/15

Project completed two weeks ahead of schedule and within projected budget.

Department of Transportation permit will be closed out after inspection by DOT official.

WBS:

Funding: PR2014-ALAMED Grant,  $60,000

             PR2012-TRLIRR Bond 5% for Trails, $42,000

             JPR Decorative Gravel Inc., $  7,230

Issues of Concern:

  • Traffic control will be an important concern during this project and steps have been taken to notify the public of the lane closures and traffic delays.
  • The project must be completed two weeks before the 2015 international Balloon Fiesta.
  • Bi-weekly progress meetings have been scheduled to ensure project is on schedule and within budget.